Barn Conversion, Llanberis 

January 2017

Client:  

Contractor: 

Architect: 

Value: 

Variations: 

Purpose: 

Duration:

 

 

 

Key Personnel: 

Mr S & Mrs S Rogers 

DBConstruction.ltd 

W M Design Ltd 

£152,000.00 

£45,000.00 

Client enhancements

24 weeks - Completion 3 weeks early. Client ordered additional works, project still finished early 

Director: David Buckley 

Project Description:

Construct new extension and refurbish old barn. Whole building was scaffolded over with weather protection measures in place to prevent and integral damage to remaining walls and features. This property was protected whilst works continued through the winter months. Difficult works such as having to use micro machinery and rock outcrops needed removing. Designed by client architect and tendered and secured by DBConstruction.ltd 

1/4